Slide 1 — Breaking Ground at Canada’s First ISR Uranium Mine

Breaking Ground at Canada’s First ISR Uranium Mine WHEELER RIVER PHOENIX MINE: VOLUME I March - August 2026

Open the original at slide 1 ↗

Slide 2 — August 24, 2024: Phoenix site after the Feasibility Field Test and prior to construction

August 24, 2024: Phoenix site after the Feasibility Field Test and prior to construction

Open the original at slide 2 ↗

Slide 3 — April 4, 2026: Initial site clearing and construction management facilities

April 4, 2026: Initial site clearing and construction management facilities

Open the original at slide 3 ↗

Slide 4 — April 14, 2026: Helicopter landing pad construction

April 14, 2026: Helicopter landing pad construction

Open the original at slide 4 ↗

Slide 5 — April 15, 2026: Heavy machinery being mobilized to site

April 15, 2026: Heavy machinery being mobilized to site

Open the original at slide 5 ↗

Slide 6 — April 18, 2026: Helicopter landing pad in use with 18-seat Airbus Super Puma

April 18, 2026: Helicopter landing pad in use with 18-seat Airbus Super Puma

Open the original at slide 6 ↗

Slide 7 — April 22, 2026: Williams Lake camp facility & exploration core yard

April 22, 2026: Williams Lake camp facility & exploration core yard

Open the original at slide 7 ↗

Slide 8 — April 30, 2026: Site preparation progress with illustrative shapes for project areas

Industrial Landfill Area Process Plant Area + Freeze Plant Area Wellfield Area (Phase 1-4 ) Site Power Substation Area Helipad Temporary Construction Management Facilities (Wellfield Phase 5) Non-Process Site Facilities, including Access Road / Gatehouse and Permanent Camp Area Misc. Pads & Ponds Feasibility Field Test (FFT) Coverall April 30, 2026: Site preparation progress with illustrative shapes for project areas

Open the original at slide 8 ↗

Slide 9 — May 19, 2026: Civil site preparation

May 19, 2026: Civil site preparation

Open the original at slide 9 ↗

Slide 10 — May 24, 2026: Aerial view of site preparation progress, with airstrip in distance

May 24, 2026: Aerial view of site preparation progress, with airstrip in distance

Open the original at slide 10 ↗

Slide 11 — June 2, 2026: 18-Seat Airbus Super Puma helicopter

June 2, 2026: 18-Seat Airbus Super Puma helicopter

Open the original at slide 11 ↗

Slide 12 — June 3, 2026: Wheeler River / Phoenix ceremonial groundbreaking on site

June 3, 2026: Wheeler River / Phoenix ceremonial groundbreaking on site

Open the original at slide 12 ↗

Slide 13 — June 4, 2026: Wheeler River / Phoenix groundbreaking celebration in Saskatoon

June 4, 2026: Wheeler River / Phoenix groundbreaking celebration in Saskatoon

Open the original at slide 13 ↗

Slide 14 — June 21, 2026: Process plant civil work

14 14 June 21, 2026: Process plant civil work

Open the original at slide 14 ↗

Slide 15 — June 29, 2026: A portion of the heavy equipment fleet on site

June 29, 2026: A portion of the heavy equipment fleet on site

Open the original at slide 15 ↗

Slide 16 — July 6, 2026: Temporary construction camp facilities

July 6, 2026: Temporary construction camp facilities

Open the original at slide 16 ↗

Slide 17 — August 4, 2026: Aggregate crushing on site

August 4, 2026: Aggregate crushing on site

Open the original at slide 17 ↗

Slide 18 — August 8, 2026: Phoenix site looking southwest with temporary camp in the distance

18 18 August 8, 2026: Phoenix site looking southwest with temporary camp in the distance

Open the original at slide 18 ↗

Slide 19 — August 8, 2026: Phase 1 wellfield area during initial freeze wall installation

August 8, 2026: Phase 1 wellfield area during initial freeze wall installation

Open the original at slide 19 ↗

Slide 20 — August 8, 2026: Process plant area, looking south with substation pad at right

20 20 August 8, 2026: Process plant area, looking south with substation pad at right

Open the original at slide 20 ↗

Slide 21 — August 8, 2026: Aggregate storage area

August 8, 2026: Aggregate storage area

Open the original at slide 21 ↗

Slide 22 — August 8, 2026: Initial concrete work begins with process plant raft slab #1

August 8, 2026: Initial concrete work begins with process plant raft slab #1

Open the original at slide 22 ↗

Slide 23 — August 10, 2026: Airstrip civil work progressing

August 10, 2026: Airstrip civil work progressing

Open the original at slide 23 ↗

Slide 24 — August 17, 2026: Phoenix site looking west, with power line clearing visible

August 17, 2026: Phoenix site looking west, with power line clearing visible

Open the original at slide 24 ↗

Slide 25 — August 19, 2026: First three process plant raft slabs at various stages of completion

August 19, 2026: First three process plant raft slabs at various stages of completion

Open the original at slide 25 ↗